Plan view — route map
Route legend
Pipeline (in Rampion 2 trench)
Grid connection spur
Cross-section — sea level → reservoir
Concept notes
- Pipeline laid in the consented Rampion 2 onshore cable trench between Climping landfall and the Bolney substation area, avoiding new corridor consenting.
- High-level reservoir on Bignor Hill (~225 m AOD) provides gross head; an in-pipe Francis or Pelton turbine sits inland of the landfall.
- Power export reuses the Rampion 2 onshore substation and existing 400 kV grid connection — no new grid infrastructure required.
- All coordinates, distances and elevations are indicative for visualisation only; not based on Ordnance Survey vector data.